This Week:

  • Hosted an LXDAO strategy discussion for phase 2, the details of which will be shared soon.
  • Discussed the possibility of moving the community call to weekends.
  • Updated the v1.1 financing deck for LXDAO and shared it with early investors, who provided valuable feedback.
  • Improved the EIPs.fun proposal and received positive feedback, and will start making a product prototype.

Next Week:

  • Share the LXDAO strategy with the community.
  • Improve the financing deck based on the strategy discussion and start contacting investors.
  • Follow up on new ideas and turn them into proposals.

Onboarding Committee

This Week:

  • Successfully onboarded a new buidler, Rockey.

Next Week:

  • Prepare for the rotation proposal.
  • Attend to routine onboarding tasks.

MobyMask Improvement

This Week:

  • Completed improvements for issues found in the last review, including the website and extension.
  • Conducted code reviews and more testing.
  • Conducted some research on the new watcher.

Next Week:

  • Make pull requests to ship the code to production and run some tests.
  • Begin work on the report history feature.
  • Follow up on MetaMask grants.

LXDAO

本周:

  • 举行了LXDAO阶段2战略讨论会,将很快分享讨论结果。
  • 讨论了将社区通话时间改到周末的可能性。
  • 更新了LXDAO的v1.1融资说明书并与早期投资者分享,收到了宝贵的反馈。
  • 改进了EIPs.fun的提案,并得到了积极反馈,将开始制作产品原型。

下周:

  • 与社区分享LXDAO的战略结果。
  • 根据战略讨论改进融资说明书并开始联系投资者。
  • 跟进新想法并将其转化为提案。

Onboarding Committee

本周:

  • 成功为一位新的buidler,Rockey,进行入职。

下周:

  • 为轮换提案做好准备。
  • 处理日常入职任务。

MobyMask Improvement

本周:

  • 完成了最近一次审查中发现的问题的改进,包括网站和扩展程序。
  • 进行了代码审查和更多测试。
  • 对新的watcher进行了一些研究。

下周:

  • 提交 PR 以将代码推向生产并运行一些测试。
  • 开始研究报告历史功能实现。
  • 跟进MetaMask的资助申请。

FrenArt

This Week:

  • Website UI design has been completed.
  • In the process of front-end and back-end coding.

Next Week:

  • Front-end, back-end, contract coding.

FrenArt

本周:

  • 已完成网站UI设计。
  • 正在前端、后端编码中。

下周:

  • 前端、后端、合约编码。

LXDAO Tools:

This Week:

  • The new onboarding process development work is 100% completed.

Next Week:

  • Will review the new onboarding process code and test it.
  • Will sort out the LXDAO website email requirements.
  • Will sort out the LXDAO website’s current bugs/features, and hire a FE to work on them.

LXP Project:

This Week:

  • Made some bug fixes, and the production deployment has been done.

Next Week:

  • The accounting team will track the previous LXP records and put them online through the LXP system.

Img3 Project:

This Week:

  • Submitted the project updates to Filecoin.
  • Tried to import the components into the LXDAO website, it’s in progress.

Next Week:

  • Post an article to introduce the Img3 project.

LXDAO工具

本周:

  • 新的入职流程开发工作已 100% 完成。

下周:

  • review 新的入职流程代码并进行测试。
  • 整理 LXDAO 官网的所有的需要发邮件的需求。
  • 整理 LXDAO 官网目前的 bug/功能,并招募一个 FE 进行开发。

LXP项目

本周:

  • 做了一些 bug 修复,生产部署也已经完成。

下周:

  • 会计团队将回溯以前的 LXP 记录,并通过 LXP 系统将记录更新到数据库并公示。

Img3项目

本周:

  • 向 Filecoin 提交了目前的项目进度。
  • 尝试将组件接入 LXDAO 官网,正在进行中。

下周:

  • 发布一篇介绍 Img3 项目的文章。

MetaPavo 项目

本周:

  • 发布新的版本
  • 发起产品方向讨论

下周:

  • 继续产品方向讨论
  • 开始部分功能裁剪

MetaPavo project

This week:

  • Release a new version
  • Initiate product direction discussions

next week:

  • Continue product direction discussion
  • Start partial feature cropping

治理小组

本周:

  • LXP 积分回溯 - 50%
  • 治理小组换届提案 - 80%
  • 活跃贡献者空投方案 - 50%
  • 社区有 buidler 出现治理方面的疑惑,进行了电话沟通

下周

  • LXP 积分回溯完成
  • 在论坛发起治理小组换届提案
  • 活跃贡献者空投方案跟进

This week:

  • LXP Point Rewind - 50%
  • Governance Group Replacement Proposal - 80%
  • Active contributor airdrop proposal - 50%
  • Community had buidler with governance concerns and made a call

Next week

  • LXP points backtracking completed
  • Proposal for governance group renewal launched in forum
  • Active contributor airdrop proposal followed up

上周

  • 完成产品原型图设计
  • 整理收集Layer2相关内容

下周

  • 产品官网设计
  • 产品研发开始
  • 产品内容完善,补充

Last week

  • Complete product prototype design
  • Organize and collect relevant contents of Layer2

Next week

  • Product official website design
  • Start of product research and development
  • Product content is complete and supplemented

DataCenter
This Week

  • Fix Docker ChromeDriver Crash Issue - 60%
  • Implement Donate3 Service - 70%

Next Week

  • Fix Docker ChromeDriver Crash Issue - 100%
  • Implement Donate3 Service - 100%
  • Investment data Api design - 100%

本周

  • 解决Docker ChromeDriver Crash问题 - 60%
  • 实现Donate3后端服务 - 70%

下周

  • 解决Docker ChromeDriver Crash问题 - 100%
  • 实现Donate3后端服务- 100%
  • 投资数据Api设计 - 100%

本周

  • 撰写 DECK 80%
  • UI和产品上的小改动 100%

下周

  • DECK 100%
  • 跟进研发进度(milestone-1:3月11日 DEMO)

This week

  • Write deck 80%
  • A few modification on the UI and Product 100%

Next week

  • Deck 100%
  • Follow up the development progress (milestone-1: DEMO on March 11)