LXDAO Weekly #34 2023.01.30 - 2023.02.05

LXDAO Weekly #34 2023.01.30 - 2023.02.05

MetaPavo
本周

  • 优化数据服务不稳定的问题
  • 暂无其他进展

下周

  • 积分回溯,proposal 补充
  • 新版产品方案软提案和讨论

MetaPavo
this week

  • Optimize the problem of unstable data service
  • No other progress

next week

  • Integral backtracking, proposal supplement
  • Soft proposal and discussion of the new product plan

DataCenter
This Week

  • Research Blur Data Api
  • Research NFT Price Predictions & POC
  • Upgrade DockerFile To Support ChromeDriver
  • Prepare High Quality User Project
  • Prepare MetaPavo Recommend Data Project

Next Week

  • Implement Blur Data Api
  • Implement NFT Price Predictions & POC
  • Prepare Address Label Data
  • Implement MetaPavo Recommend Data Service

本周

  • 调研blur数据api
  • 调研NFT价格预测 和 实现POC
  • 升级爬虫DockerFile去支持ChromeDriver
  • 准备高质量用户项目
  • 准备MetaPavo推荐数据项目

下周

  • 实现blur数据api
  • 实现NFT价格预测 和 实现POC
  • 准备地址标签数据
  • 实现MetaPavo推荐数据服务

LXDAO Tools:

This Week:

  • Added the LXDAO Influence data in the LXDAO website mission section.
  • Updated LXDAO Partners in the LXDAO website.
  • Restarted the new onboarding process project, clarified some product details with the new developer.
  • The LXDAO website email integration has been deployed in Dev environment, it’s in test process.

Next Week:

  • Started the new onboarding process project development work.
  • Will deploy email integration change into production environment.

LXP Project:

This Week:

  • Made some UI and copy changes, it’s in the testing process, also had some discussions with team to clarify what is LXP, no impacts to our current project.

Next Week:

  • Finish the testing in Dev environment, will deploy it into production environment.

Img3 Project:

This Week:

  • Reviewed the document website, and made some improvements, the document homepage design is in process.

Next Week:

  • Complete the document homepage design change, then will publish it.

LXDAO工具

本周:

  • 在 LXDAO 官网 mission 部分增加了 LXDAO 影响力数据。
  • 在 LXDAO 官网上添加了 LXDAO 合作伙伴链接。
  • 重新启动了新的入职流程项目,与新的开发人员确认了一些产品细节。
  • LXDAO 官网的邮件集成已经部署在开发环境,正在测试过程中。

下周:

  • 开始新的入职流程项目开发工作。
  • 部署电子邮件集成改动到生产环境中。

LXP项目

本周:

  • 做了一些 UI 和文案的修改,正在测试过程中,也和团队进行了一些讨论,明确了什么是 LXP,对我们目前的项目没有影响。

下周:*

  • 完成开发环境的测试,将部署到生产环境。

Img3项目。

本周:

  • Review 了组件的文档网站,并做了一些改进,文档主页的设计正在进行中。

下周:

  • 完成文件主页的设计修改,然后发布。

MyFirstLayer2

This week

  • For core team recruitment, there are currently 1 designer, 1 contract developer, 1 content writer and 1 project manager
  • Carry out the first staff meeting to explain the project launch plan, contribution mechanism, team configuration and allocation mechanism
  • MVP stage points settlement, 1v1 to confirm that everyone’s points are correct;

Next week

  • Team recruitment, advisory group and front-end research and development;
  • Announce team recruitment.

本周

  • 进行核心团队招募,目前可确定有设计师1名、合约开发1名、内容编写1名,项目管理1名
  • 开展第一次全员会议,讲解项目启动计划,贡献机制,团队配置,分配机制
  • MVP阶段积分结算,1v1确认每个人积分无误;

下周

  • 团队招募,顾问团和前端研发;
  • 公布团队招募情况。

LXDAO

This Week:

  • Finished the first version of the LXDAO financing deck, reviewed it with the financing preparation team, and met one investor
  • Followed up on ERC+86 event plans, will have a better structure and plans for hosting it. Bruce will keep following up on it
  • Followed up on the FVM hackathon and will submit the work next Monday
  • Applied for Network State hackathon
  • Built a connection with BeWater

Next Week:

  • Month AMA
  • Improve financing deck and start meeting more investors
  • LXDAO Shanghai IRL meetup
  • Build more connections and collaborations

Onboarding Committee

This Week:

  • No buidler joined. A few applicants in the process
  • Starting handling applications, created seven buidler application proposals
  • Transferred the self-onboarding UI developments to other developers

Next Week:

  • Continue onboarding buidlers
  • Start working on the self-onboarding UI developments
  • Make a proposal for the new Onboarding Committee rotation

MobyMask Improvement

This Week:

  • Discussed the blocking issues and solution with Dan
  • Pushed the progress for the Website and Extension. UI/UX polishing, RWD support, and logic testing are the remaining tasks. Overall, the progress is over 75%
  • We decided to leave the Report History feature late and focus on what we can do for now
  • Our estimation is to finish the Website and Extension next weekend, and deploy them to review, later will improve based on the feedback and start working on the Report History feature

Next Week:

  • Polishing UI/UX, RWD support, logic testing, etc.
  • Improve based on the designer and product manager’s reviews
  • Finish the Extension, and can be installed and tested by using the local development installation

LXDAO

这周:

  • 完成了 LXDAO 的第一版融资方案,与融资准备团队一起审查,并会见了一位投资者。
  • 跟进了 ERC+86 活动计划,将有更好的结构和举办计划,Bruce 将继续跟进此事
  • 跟进 FVM 黑客马拉松,将在下周一提交作品
  • 申请参加网络国家黑客马拉松
  • 与 BeWater 建立了联系

下周:

  • 月度 AMA
  • 完善融资平台,开始与更多的投资者见面
  • LXDAO 上海 IRL 会议
  • 建立更多的联系和合作
  • 入职委员会换届

Onboarding Committee

这周

  • 没有建设者加入。有几个申请者正在处理中
  • 开始处理申请,创建了七个 buidler 申请提案
  • 将自助入职的UI开发工作移交给其他开发者

下周

  • 继续加入 buidler 的工作
  • 开始进行自助入职的用户界面开发工作
  • 为新的入职委员会的轮换做出提议

MobyMask Improvement

这周

  • 与 Dan 讨论了阻塞的问题和解决方案
  • 推进网站和扩展的进展。UI/UX 抛光,RWD 支持,以及逻辑测试是剩下的任务。总的来说,进度超过75%
  • 我们决定推迟报告历史功能的开发,把重点放在我们目前能做的事情上
  • 我们预计在下周末完成网站和扩展,并将其部署到审查中,随后将根据反馈意见进行改进,并开始报告历史功能的工作

下周

  • 优化 UI/UX,支持 RWD,逻辑测试,等等
  • 根据设计师和产品经理的评论进行改进
  • 完成扩展,并可以使用本地开发安装的方式进行安装和测

Governance Group

This week:

  • Deck governance and operational data collation
  • Accounting team formed, initial personnel identified, Marcus, ache
  • LXP Model Architecture Discussion
  • Developing a process for project proposal presentations
  • Additional items in the Conscience Pack: Stickers

Next week.

  • LXDAO contributor airdrop programme design
  • Accounting team groundwork collation
  • Support for the creation of operational team proposals
  • Preparation for the change of governance group

治理小组
本周:

  • Deck 治理和业务数据的整理
  • 会计小组:初步确定人员,Marcus,ache
  • LXP 模型架构讨论
  • 制定项目提案宣讲会的流程
  • 良心大礼包增设物品:贴纸

下周。

  • LXDAO 贡献者空投方案设计
  • 会计团队基础工作的整理
  • 支持建立运营小组提案
  • 治理小组换届的准备工作

8DAO Member System

This Week:

  • Solve the backend ci/cd problem.
  • Front-end and back-end coding.

Next Week:

  • Complete front-end and back-end coding.

8DAO会员系统

本周:

  • 解决后端ci/cd问题。
  • 前端、后端编码。

下周:

  • 完成前端、后端编码。

Donate3

本周

  • 发起Donate3 重启提案
  • 在社区内完成一次关于提案的宣讲

下周

  • 完成产品的UI设计(MVP版本)
  • 完成功能拆解后的需求文档
  • 动员和组织团队,明确工作角色和任务分配

This week

  • Initiate Donate3 restart proposal.
  • Organize a presentation about donate3 in the community.

Next week

  • Complete the UI design (MVP version)
  • Complete the requirement document after functional disassembly (MVP version)
  • Organize team members who are interested in donate3, clarify job roles and assignments